General renovation of an old hydroelectric power plant
Historical view
The mill in Brudnice was built in 1873. The historic turbine comes from 1907. The mill probably belonged to the neighboring manor complex since the 15th century. So it happens that the first mill located around the same area is also mentioned approximately at that period.
Parameters
Technologies used
- SCADA IT system
Cooperation with the client included comprehensive implementation of the project consisting of renovation of a small hydropower plant (SHPP) on Wkra river.
Consulting and design
Optimization of the power plant design
Post-completion documentation
Execution of construction works as a general contractor
Delivery of a complete hydroset equipped with a vertical Kaplan turbine
Carrying out works to construct electrical installation and power plant’s control and automation systems based on a PLC controller and equipped with a HMI input panel
Implementation of the SCADA IT system allowing for real-time monitoring of the power plant operating parameters
Inlet grate
Weir’s flushing outlet rotary gate, its bearing nodes equipped with water-lubricated bearings
Service gate equipped with a de-icing heating system
Drive and control systems of the gates